For a while, the most visible sign of the work at Hidden Gardens Nursery & Tea Room was dust. The shop's owner told KETK in March that dirt from the construction "was blowing over my counters, it would get on the porch, on the chairs," and that she was glad the dirt work was finally finished. She also said the construction hadn't hurt her business. The shop is at 967 FM 2493 W, inside the work zone.
The dirt work she was glad to see end tells you a lot about the order of the project. In Bullard, the new road opened first and the bridge comes last. The realigned FM 2493 has carried traffic since March, and that is the route drivers will keep. The work still ahead, which TxDOT now expects to run into spring 2029, is mainly about raising US 69 over that intersection. If you drive through town every day, the route you've used since spring is the long-term one. The detours from here on are mostly on the highway.
The Road Moved First, in March
During the week of March 9, 2026, traffic moved onto the newly built, realigned section of FM 2493/Old Jacksonville Highway where it meets US 69. The Tyler Morning Telegraph reported that the old stretch of FM 2493, S. Houston St south of CR 3801, closed to through traffic once the switch took effect.
The new route links the town's two school campuses. KETK described it as a detour near Bullard High School onto the newly repaved FM 2493, which now reaches Highway 69 right in front of Bullard Middle School: "a mile-long straight shot between the two campuses." TxDOT's Jeff Williford told the station:
"It can be a little confusing. Plan ahead, maybe leave a little bit early."
Williford was talking about school drop-off, and his advice still applies. The middle school intersection got attention before the switch, too. KLTV reported in December 2025 that Bullard ISD had announced a drop to 45 mph at US 69 and FM 2493 East in front of the new middle school starting the week of Dec. 19, followed by a temporary traffic signal planned for Jan. 5. That signal was described as temporary, and the plans don't yet say what the finished interchange will mean for each nearby street and driveway. Until TxDOT says so directly, treat the current signals and turns as the construction-period setup.
KETK also reported that Houston Street "will become a four-lane highway leading to that new overpass." TxDOT's FM 2493 project page describes the same direction for the whole corridor. It calls for widening the road from two lanes to four divided lanes, adding a continuous left-turn lane, providing bicycle and pedestrian facilities where applicable, and realigning FM 2493 to meet FM 2493-East at US 69.
US 69 Narrowed in September
With FM 2493 on its new route, the work moved to the highway. On Monday, Sept. 28, US 69 through Bullard shifted to its east side so crews could start building on the west side. According to CBS19, the setup includes:
- One lane in each direction
- A continuous center left-turn lane
- A start time after 8 a.m. that Monday, chosen to avoid adding congestion during school drop-off
- An expected duration of "several months"
TxDOT's project update for the week of Oct. 26, 2026 confirms the lane reduction is still in place and repeats the "several months" estimate. By Thursday, Nov. 5, the narrowed highway will have been in place for more than five weeks. Based on TxDOT's own wording, plan on it lasting well into 2027.
The same update describes what crews are building. The work includes an overpass with entrance and exit ramps, the FM 2493 realignment west of US 69, new bridges, paving, pavement markings and signs. The work zone runs along US 69 from half a mile north of FM 2493 West to half a mile south of FM 2493 East, and along FM 2493 from 0.3 miles south of FM 344 to US 69. The contractor is East Texas Bridge, Inc., and the cost is listed at $68 million.
Two Projects, Two Finish Lines, Both Later Than First Announced
Two TxDOT projects overlap around Bullard, and their schedules are easy to confuse. The overpass covers the crossroads itself. North of it, a separate widening of FM 2493 runs from FM 346 in Flint down to just south of FM 344, and that is the road most Bullard commuters take toward South Tyler. KETK described both as part of a 14-mile corridor from Loop 323 in Tyler to US 69 south of Bullard. The plan behind them goes back years. A 2016 Tyler Area MPO study of FM 2493 from Loop 323 to US 69 in Bullard recommended widening the corridor, according to a 2023 TxDOT public-meeting script.
Both projects have slipped since earlier coverage:
| Project | Earlier published estimate | Current TxDOT estimate, week of Oct. 26, 2026 |
|---|---|---|
| US 69 / FM 2493 overpass and realignment | Fall 2028, per KETK in March 2026 | Spring 2029, $68 million |
| FM 2493 widening, Flint to south of FM 344 | Spring 2027 and $52 million, per KLTV in December 2025 | Fall 2029, $78.5 million |
KETK noted in March that the Fall 2028 date was already almost a year later than the original target. The newer TxDOT figures add a few more months to the overpass. They also move the widening from Flint by two and a half years, and its cost rises from $52 million to $78.5 million. For someone driving between Bullard and Tyler, the widening is now expected to finish after the overpass, so FM 2493 will probably be the last part of the drive to see construction cones go away. Contractor Longview Bridge and Road LTD has crews working throughout that stretch, and TxDOT asks drivers to use caution.
For trips toward Flint and Tyler's south side, the widening on FM 756 is a separate project. TxDOT lists daytime lane closures there while crews build cross culverts and temporary signals at Jeff Davis Drive, with completion expected in spring 2030.
Downtown, Next to the Work Zone
The overpass is being built close to downtown, and that has people thinking about downtown traditions. In March, a resident told KETK she was worried about Spring Fling: "They're going to do that overpass. And the Spring Fling is usually right there on the grass downtown and there will be no room for it."
Spring Fling still took place this year. KETK's spring events roundup listed the 2026 event for Saturday, April 25, hosted by Coffee Around The Corner, with food trucks, shopping and family activities. An event listing gave the location as 202 B West Main Street and the hours as 10 a.m. to 4 p.m. No location for 2027 has been announced. With the overpass scheduled for completion in spring 2029, Spring Fling has two more springs with construction nearby, and it's worth watching how the organizers handle them.
Main Street businesses keep opening while the highway work continues. In June, the Tyler Morning Telegraph reported that the Moody Family Wines tasting room at 201 W. Main St. had permanently closed. By October, the same paper's Business Beat column reported that Rejuvenate You & Co. and Salt & Light Spa by Jessica share that address and offer medical aesthetics and skincare services.
The June column also named a vacant lot near US 69 and Robert Walker Road as the planned site of a new McDonald's, estimated to finish by the end of the year. That was a projection made in June, so check for an opening announcement before planning a stop.
Dates on the Bullard Calendar Through December
The city's regular schedule continues during construction. These dates come from the City of Bullard's November calendar and December calendar:
- Nov. 12: Bulky-item pickup on the west side of 2493, except Windsor Estates
- Nov. 26: Bulky-item pickup on the east side of 2493, including Windsor Estates
- Dec. 8: City Council meeting at 6 p.m.
- Dec. 10: Bulky-item pickup, west side
- Dec. 24: Bulky-item pickup, east side
The pickup schedule is split by which side of 2493 you live on, so the east and west sides have different dates. The calendar doesn't yet list this year's Magic on Main or the Christmas parade. Last year's parade was held Saturday, Dec. 6, 2025, so watch the city's page for the 2026 date. TxDOT's Tyler District posts updates every week, and the US 69 lane reduction is the item to check for the next change.
At Sovereign Place Real Estate, we keep track of how projects like this change daily life in the places we serve, from the drive to school to which storefronts on Main Street are open. If you're planning a sale, a move or a renovation in Bullard and want to talk through how the work at US 69 and FM 2493 might affect your timing, we're happy to start that conversation.